I. STRUCTURAL/CIVIL WORKS
Structural Frames
- Foundation/Footing
- Footing Tie Beam
- Columns
- Slab on Fill
- Beams
- Suspended Slab
Isolated Footing, Cast in Place reinforced Concrete
Cast in Place reinforced Concrete
150mm x 350mm (min section) Cast in Place Concrete
75mm (min thickness) Cast in Place Concrete
150mm x 350mm (min section) Cast in Place Concrete
90mm (min thickness) Cast in Place Concrete
Reinforcing Steel Bars Grade 33, 16mm dia. standard size for Beams and Columns
Grade 33, 10mm dia. standard size Stirrups and Lateral Ties
Grade 33, 16mm dia. standard size for Footing
Grade 33, 10mm dia. standard size Slabs
Concrete 3000 psi at 28 days for Foundation, Columns, Beams, Slab
Roof Framing 2500 psi at 28 days, for Slab on fill
2000 psi (minimum) at 28 days, for lean concrete
Roof Framing Steel Roof Framing System
II MASONRY
Exterior Walls 125mm (5'") CHB with 2" (minimum) Plaster cover
with 600mm x 600mm steel reinforcement (10mm diam)
Interior Walls 100mm (2") CHB with 2" (minimum) Plaster cover with
600mm x 600mm steel reinforcement (10mm diam)
Lintel Beams and Lintel Columns Cast in place lean concrete with 10mm diam reinforcement
III. GROUND/FOUNDATION All ground and foundation rest are excavated to depth graded and compacted accordingly. Provision of 2" (50mm) thk gravel fill prior to concrete pouring for footing, footing tie beam and slab on fill.